River Island's Turn Onto Furys Ferry Is Finished. The Road Around It Has a Few Months to Go.

  • Caleb Fairey
  • October 22, 2026

If you live in River Island, your part of the Furys Ferry Road widening is done. The four-way stop at Blackstone Camp Road, where every trip out of the neighborhood used to start, is now a traffic signal. It went into flash mode on July 29 and turned fully live in early August. The rest of the project is still underway. In late September, crews moved southbound traffic onto new pavement between Hardy McManus Road and North Belair Road, and the county hasn't given a firm finish date. A separate state resurfacing contract on the Augusta stretch of Furys Ferry runs until March 31, 2027.

So the orange cones won't all disappear at once. They'll clear in stages, and the stage closest to River Island cleared first.

The Light at Blackstone Camp Road

You get out of River Island the same way whichever direction you're headed. Columbia County's road index puts River Island Parkway off Blackstone Camp Road, and Blackstone Camp Road off Furys Ferry Road. That means the Furys Ferry and Blackstone Camp intersection, which Colony Drive also feeds into, is where the neighborhood's daily traffic meets the main road.

That intersection was a four-way stop for years. WRDW reported that the new signal went online on a Wednesday morning in early August, replacing the stop signs. Project engineer Kelly McDaniel told the station why it mattered:

"No longer do they have to start out there in the middle of the traffic. And we've had so many accidents at this point, at this stop here. It should provide them a better idea of exactly how good the final product will be for them."

McDaniel's last line is the useful one. The Blackstone Camp signal is a finished piece of the final road. The Augusta Newsroom described it as a step toward wrapping up the larger expansion, which runs from Evans to Locks Road toward the Savannah River and ends with four lanes.

The signal was also tested before it went live. WFXG reported that it went into flash mode on July 29, about a week before it started cycling.

How the Crews Keep Traffic Moving While They Build

The traffic shifts south of Blackstone Camp follow a pattern. In February, Kyle Titus, Columbia County's director of engineering services, explained it to WJBF. Crews pave the shoulders and top one section. "Then they're going to shift traffic over into the currently closed lane and move their construction forces to where traffic is now," he said.

In other words, crews build a new section, move traffic onto it, then rebuild the lanes the cars just left. Here's how that has played out between Hardy McManus Road and North Belair Road this year:

  1. Late February 2026. E.R. Snell crews worked from Hardy McManus Road to the state line, preparing the road for resurfacing. Titus said paving was the critical path because it can only happen when temperatures are high enough and rising.
  2. March 23, 2026. All lanes between North Belair Road and Hardy McManus Road were scheduled to move onto a new section on the east side of the right-of-way, and a new roundabout was set to open at Furys Ferry and Hardy McManus, according to The Augusta Press.
  3. July 29 and early August 2026. The Blackstone Camp Road signal went into flash mode, then went live.
  4. Week of September 28, 2026. Southbound traffic at the Hardy McManus roundabout heading toward North Belair moved from the old pavement onto new pavement on the west side. Daytime lane closures from 9 a.m. to 2:30 p.m. were scheduled between Hardy McManus and North Belair and at the Mullikin Road intersection, according to a county release published by Augusta Good News.
  5. October 4 to 11, 2026. Overnight lane closures on Hardy McManus Road between Furys Ferry Road and William Few Parkway were moved to this week, from 7 p.m. to 7 a.m.

The March move went east and the September move went west. That's the leapfrog Titus described: traffic moved onto new east-side pavement in spring, and by fall the new west-side pavement was ready for southbound cars. When you drive through the Hardy McManus roundabout this month, you're on the second half of that sequence.

Why "End of 2026" Is Still a Soft Date

The timeline has moved more than once. The widening contract was signed in April 2021, WFXG reported, and the station said many of the 39,000 vehicles that use the road's intersection with Evans to Locks each day had been dealing with it since.

In February, WJBF reported that Hurricane Helene and other weather had pushed completion back several months. At that point Titus said the county was on target to finish by mid-summer. Mid-summer came and went with work still going. In WFXG's later report, county officials said they tentatively expected to finish by the end of 2026, but they had no firm date and the work could run into 2027.

Paving is the reason the date keeps slipping. As Titus explained it, asphalt goes down only when the temperature is high enough and rising. On cold days, crews switch to curb and gutter, sidewalks, and driveways. Late fall and early winter have fewer good paving days than summer. Any section still waiting for its top layer when the weather turns could wait into the new year, which matches the county's own caution about a 2027 finish.

The Same Contractor, a Second Contract

Even after the county widening wraps up, Furys Ferry won't be completely free of work zones. In May, WRDW reported that the Georgia Department of Transportation awarded E.R. Snell Contractor a $2.11 million contract to resurface nearly three miles of Furys Ferry Road between Riverwatch Parkway and Evans to Locks Road. The completion date is March 31, 2027.

E.R. Snell is also the contractor on the county widening.

County widening

GDOT resurfacing

What it does

Widens Furys Ferry to four lanes

Resurfaces nearly three miles of Furys Ferry

Where

From Evans to Locks Road toward the Savannah River

Riverwatch Parkway to Evans to Locks Road

Contractor

E.R. Snell

E.R. Snell Contractor, Inc.

Dollar figure reported

Not given in current reporting

$2.11 million

Timing

Tentatively end of 2026, possibly into 2027

Completion date of March 31, 2027

For a River Island driver, the two projects cover different directions. The county widening is the work you pass on the Columbia County side. The GDOT contract covers the stretch toward Augusta, ending at Riverwatch Parkway. The late-September traffic shift belongs to the first project. A milling crew you might see over the winter on the Augusta end would most likely belong to the second.

Two Newer Stops Along the Way

This year, a couple of new businesses opened along the same road while it was still under construction.

Griffin's Steakhouse, The Commons at West Lake.Augusta Business Daily reported in June that a husband-and-wife team with food service experience leased a large space at The Commons at West Lake on Furys Ferry Road. The space includes a dining area with a roll-up garage door, and it sits between the Cucumber & Mint retail store and BenchMark Physical Therapy, down from Ironwood Tavern and across from Rooted Coffeehouse. The paper said a July opening was expected. The restaurant's website now lists it at 1040 W. Lake Commons Drive in Martinez, says "Open now," and posts its hours. The Commons sits outside the West Lake neighborhood, close enough to River Island for a weeknight dinner.

Dog & Cat Co., Furys Ferry Station. This locally owned pet store is near Riverwatch Parkway, at the Augusta end of the GDOT resurfacing stretch. In August, Augusta Business Daily described a shop selling pet food, treats, toys, accessories, and gifts, along with the owner's own line of homemade dog food. It also has a patio meant for pets and their owners. The paper reported a planned grand-opening week of September 7 to 12. The store's website lists the address as 231 Furys Ferry Road. Hours are 10 a.m. to 6 p.m. Tuesday and Wednesday, 11 a.m. to 7 p.m. Thursday and Friday, and 10 a.m. to 2 p.m. Saturday. It's closed Sunday and Monday.

Both businesses are on parts of Furys Ferry where roadwork is still underway or scheduled. Dog & Cat Co. is closed Mondays and Griffin's posts its own hours online, so check those before you go, along with the county's weekly traffic notices.

For the drive you make most, the change is already in place. Every trip out of River Island starts at the Blackstone Camp Road signal, which has been running since early August. The work that remains is south of that turn, between Hardy McManus Road and North Belair Road, and on the Augusta stretch scheduled for resurfacing by March 31, 2027. For more on the neighborhood, see our River Island page and our guide to the paddle routes that start at River Island's dock.

If you're thinking about listing a River Island home while Furys Ferry is still being finished, the Fairey Team can build a marketing plan around the new signal at Blackstone Camp Road and around when the remaining construction is expected to clear. Get a free home marketing plan, sell smarter and give back.

Disclosure. This post is general information only, not legal, tax or financial advice. Laws, programs, rates and figures change, so verify the details with the appropriate licensed professional before you act. Fairey Team is a real estate team with eXp Realty, licensed in Georgia, and does not provide legal, tax or lending services. Equal Housing Opportunity.

Let's Find Your Dream Home

Work with them for high-performance real estate service in the Evans area. Their expert market knowledge, strong track record, and client-centered focus ensure your buying or selling journey is confident and rewarding.

Follow Me on Instagram